Slide 1: Rye Park Wind Farm CCC Meeting
RYE PARK WIND FARM CCC MEETING 21 JUNE 2022
Slide 2: Contents
CONTENTS 1. PROJECT UPDATE 2. SCHEDULE OF WORKS 3. YASS STREET, RYE PARK VILLAGE – FOOTPATH UPDATE 4. ENVIRONMENT AND COMPLIANCE MODIFICATION TO PROJECT APPROVALS 5. STAKEHOLDERS AND COMMUNITY FEEDBACK, ENQUIRIES & COMPLAINTS CCC MEMBERS 6. PROJECT BENEFITS EMPLOYMENT BENEFIT SHARING PROGRAMS RPWF C
Slide 3: Schedule of Works: Indicative Schedule
SCHEDULE OF WORKS INDICATIVE SCHEDULE Project Programme: • Construction will include road upgrades, wind farm construction (not including pre-construction activities) and commissioning - Construction Commencement – 1 December 2021 - Commissioning – From Late 2022 - Operations – Early 2024 Month from
Slide 4: Schedule of Works: Transport, Road Upgrades & Schedule
SCHEDULE OF WORKS TRANSPORT, ROAD UPGRADES & SCHEDULE Road Upgrades Update: • Site Entry Intersections – Complete. • Grassy Creek Road – Pavement and drainage works 90% complete. Sealing works complete. • Boorowa Bypass – Pavement and drainage works complete. Sealing complete. Causeway complete • Bo
Slide 5: Cooks Hill Road Upgrade Update
SCHEDULE OF WORKS TRANSPORT, ROAD UPGRADES & SCHEDULE Cooks Hill Road upgrade – update • Tilt Renewables continue to work with Upper Lachlan Shire to finalise the design of the Cooks Hill Road upgrade. • The final design is being developed to address key biodiversity and heritage constraints, whilst
Slide 6: Project Update: What Have We Been Up To
PROJECT UPDATE WHAT HAVE WE BEEN UP TO Wind Farm Works • Temporary Compound Facility – Stage 2 of office setup underway • Temporary batch plant installed and being commissioned in northern section • Earthworks continue in the northern and central areas heading towards the northern and southern sub s
Slide 7: Project Update: What Have We Been Up To
PROJECT UPDATE WHAT HAVE WE BEEN UP TO • Public road upgrades continuing • Earthworks on site ongoing – New areas commenced • ARDG quarry supply update: • ARDG have commenced operations in Fairburn and material is being supplied to the RPWF via the internal access points • ARDG have commenced prepar
Slide 8: Project Update: Works on Site
PROJECT UPDATE WORKS ON SITE Completed wind farm access track and rehab WTG hardstand construction Tilt Renewables Presentation Title - Date 2019 8
Slide 9: Yass Street, Rye Park Village Footpath Update
YASS STREET, RYE PARK VILLAGE FOOTPATH UPDATE As part of the Wind Farm Project, we are upgrading Yass Street to ensure that it is suitable and safe during construction, and further to minimise traffic impacts for local residents. In addition to this development requirement, Council requested that th
Slide 10: Environment & Compliance: Modification to Project Approvals
ENVIRONMENT & COMPLIANCE MODIFICATION TO PROJECT APPROVALS Modification Development EPBC Approval Consent • Several optimisations to the access track design to allow for the efficient delivery of the Project (SSD 6693-MOD1) (EPBC 2020/8837) • Largely proposed to address challenges of constructabilit
Slide 11: Environment & Compliance: Compliance
ENVIRONMENT & COMPLIANCE COMPLIANCE Safety • 1 incident recorded and closed out relevant regulatory notifications undertaken, leading indicator reporting trending positively. • COVID-19 Management Protocols remain in place in accordance with NSW regulations/guidelines incl. Rapid Antigen Testing, an
Slide 12: Environment & Compliance: Compliance
ENVIRONMENT & COMPLIANCE COMPLIANCE Biodiversity Management S&I contractor included in monitoring and booking systems • Pre clearance surveys continue prior to works commencing in: Heritage management • Native vegetation sections along the public road work upgrade • Cultural heritage salvage has bee
Slide 13: Feedback, Enquiries & Complaints
STAKEHOLDER & COMMUNITY ENGAGEMENT FEEDBACK, ENQUIRIES & COMPLAINTS Communication • Newsletter – June issue out soon • Fortnightly construction updates continue w focus on public road upgrades – via email and in community noticeboards • SMS updates continue – to direct subscribers to read the full u
Slide 14: Project Benefits: Benefit Sharing
PROJECT BENEFITS BENEFIT SHARING Benefit Sharing initiatives update • The Outpost Food Van is now open from 7am – 3pm daily, serving up hot food and quality coffee. Pete has lots of ideas and is keen to support community initiatives at the Rec Grounds and with the Rye Park school. • The Rye Park Win
Slide 15: Project Benefits: Employment
PROJECT BENEFITS EMPLOYMENT Local subcontracts awarded include: • Concrete Supply for Turbines – Hanson (national) • Reo Installation Turbine Foundations and OHL – Stride Employment Opportunities Reinforcement (Yass) • Goods & Services Register – monthly update to contractors • Civil Area 8 Earth Wo
Slide 16: Discussion