Slide 1: Energy Developments Limited 2008 Annual General Meeting – Managing Director's Address
Energy Developments Limited (ENE) 2008 Annual General Meeting – Thursday 6 November 2008 Managing Director’s Address Thank you Mike. Mike has already highlighted the overall financial performance for the year. I will now provide you with an update on the business, together with financial guidance fo
Slide 2: West Kimberley project in commercial operation
The West Kimberley project is in commercial operation. It is undoubtedly one of the Company’s most ambitious projects to date. The last 60-day reliable operations test was passed at Broome Power Station in June after gas quality variations caused interruptions on three earlier occasions. This was ve
Slide 3: Financial Year 2008 and regional performance
This is an important milestone for the Company being the first major project constructed under a turnkey contract by a third party. This approach minimises the Company’s exposure to the material construction risks experienced in the West Kimberley project and signals the Company’s preferred approach
Slide 4: Europe
Europe The Company’s UK LFG business continued to be strong performer, with EBITDA up 8% to $24.0 million for the year, notwithstanding the adverse impact of the higher Australian dollar. This improved result was driven by access to higher market-based power pricing at certain sites, good gas field
Slide 5: Carbon regulation and renewable energy policy
It is illogical that companies like EDL that have led the way in carbon abatement technology and know-how may be penalised simply because we moved early. We remain actively engaged with both Commonwealth and State governments to minimise any potential unintended consequences as a result of the intro
Slide 6: NGAC price, Strategic Review costs and outlook
As noted above the spot NGAC price has recently fallen, to approximately $5/NGAC for some of the reasons outlined earlier. If this price is sustained in the short term the Company will consider the impairment of our expected unsold NGAC inventory on hand at 31 December 2008 – this of course will be
Slide 7: Welcome to Energy Developments Limited Annual General Meeting
Welcome to Energy Developments Limited ANNUAL GENERAL MEETING Held at the Sofitel Hotel Brisbane at 2pm on Thursday 6 November 2008
Slide 8: West Kimberley Power Project
West Kimberley Power Project
Slide 9: Managing Directors Address: Update
Managing Directors Address West Kimberley Power Project Update ▲ Broome Power Station Opening Ceremony April 08 ▲ LNG Fuelled Road Train
Slide 10: Fuel Storage Facility – Broome
Managing Directors Address West Kimberley Power Project Fuel Storage Facility – Broome
Slide 11: LNG Plant - Karratha
Managing Directors Address West Kimberley Power Project LNG Plant - Karratha
Slide 12: Derby Power Facility
Managing Directors Address West Kimberley Power Project Derby Power Facility
Slide 13: Halls Creek Power Facility
Managing Directors Address West Kimberley Power Project Halls Creek Power Facility
Slide 14: Moranbah North Power Project
Moranbah North Power Project
Slide 15: Moranbah North Power Project Power Station
Managing Directors Address Moranbah North Power Project Power Station
Slide 16: Moranbah North Power Project Update
Managing Directors Address Moranbah North Power Project Update ▲ Grid Connected ▲ Jenbacher Engine
Slide 17: Thank you for attending
Thank you for attending Energy Developments Limited ANNUAL GENERAL MEETING