Slide 1: Investor Meetings March 10-14, 2011
Investor Meetings MARCH 10-14, 2011
Slide 2: Safe Harbor Provisions
Safe Harbor Provisions This presentation contains statements concerning NU’s expectations, beliefs, plans, objectives, goals, strategies, assumptions of future events, future financial performance or growth and other statements that are not historical facts. These statements are “forward-looking sta
Slide 3: Safe Harbor Provisions
Safe Harbor Provisions Information Concerning Forward-Looking Statements In addition to historical information, this communication may contain a number of “forward-looking statements” as defined in the Private Securities Litigation Reform Act of 1995. Words such as anticipate, expect, project, inten
Slide 4: Topics for Today
Topics for Today • Merger status • NU - 2010 results and stand-alone 2011 outlook • NU - Transmission segment • NU - Electric distribution/generation segment • NSTAR – Company update
Slide 5: A Compelling Combination – Creates Largest Utility Company in New England
A Compelling Combination – Creates Largest Utility Company in New England Significant transmission investment opportunities combined with balance sheet strength provides for substantial growth potential Larger, more diverse and better positioned to support economic growth and renewables in New Engla
Slide 6: Key Merger Terms
Key Merger Terms Expected to close in the second half of 2011 Timing / Approvals: Headquarters: Dual – Hartford and Boston Company Name: Northeast Utilities Consideration: 100% stock Exchange Ratio: 1.312 shares of Northeast Utilities per NSTAR share Pro Forma Ownership: 56% Northeast Utilities shar
Slide 7: NU-NSTAR Merger Status
NU-NSTAR Merger Status • NU and NSTAR shareholders approved the merger by needed two-thirds votes on March 4 • Hart-Scott-Rodino waiting period expired in February without objection • FCC review complete without objection • FERC, NRC reviews pending • MA DPU discovery under way, ruling expected soon
Slide 8: Improving Earnings in Distribution/Generation Businesses
Improving Earnings in Distribution/Generation Businesses $27.1 $47.5 $12.3 $41.4 $70.0 $21.0 $16.7 $74.0 $32.7 $10.1 $69.3 $94.1 $0.0 $10.0 $20.0 $30.0 $40.0 $50.0 $60.0 $70.0 $80.0 $90.0 $100.0 CL&P PSNH WMECO Yankee Gas
Slide 9: 2010 Results and Standalone 2011 Guidance
2010 Results and Standalone 2011 Guidance 2009 Actual 2010 Actual 2011 Guidance NU Consolidated EPS (GAAP) $1.91 $2.19 $2.10 - $2.25 Distribution/Generation $0.92 $1.16 $1.25 - $1.35 Transmission $0.95 $1.00 $1.05 – $1.10 Competitive $0.09 $0.05 N/A NU Parent/Other ($0.05) ($0.05)* ($0.05)** NU Cons
Slide 10: Final Resolution of All Three Electric Rate Cases
Final Resolution of All Three Electric Rate Cases • Five-year settlement approved by NHPUC on 6/28/2010 • $45.5 million increase on 7/1/10 in addition to 8/1/09 temporary increase of $25.6 million • $2.9 million decrease on 7/1/11 • 2012 & 2013 projected increases of $9.5 million & $11.1 million • A
Slide 11: Transmission Business Strategy: Major Initiatives Expanding Across Wider New England Geography
1 2 Transmission Business Strategy: Major Initiatives Expanding Across Wider New England Geography 3 4 Southwest Connecticut Reliability: Projects Complete Connecticut Borders (MA, RI) : NEEWS Projects Under Way NPT HVDC Northern Pass Transmission (NPT) Line between Quebec and New Hampshire Renewabl
Slide 12: Slide 12
Slide 13: NEEWS Projects Advance Current Status Report
NEEWS Projects Advance Current Status Report Greater Springfield Reliability Project • Received siting approval in CT and MA • Development and Management Plans approved by CT Siting Council • Substation construction commenced in MA in Dec. • Commenced overhead construction in MA in February 2011 • C
Slide 14: Northern Pass Transmission – a $1.1 Billion Capital Investment
Northern Pass Transmission – a $1.1 Billion Capital Investment ´ • To be owned by Northern Pass Transmission LLC - NU (75%) and NSTAR (25%) • 1,200 MW transfer capability • Northern terminus at Des Cantons (Québec), southern terminus in Franklin (New Hampshire) • Québec terminal will convert the pow
Slide 15: Northern Pass Transmission - Project Milestones as of 3/1/11
Northern Pass Transmission - Project Milestones as of 3/1/11 Q4 2011 Begin long lead time material procurement $ 1.1 Billion Project cost - (U.S. side) Late 2015 In-Service Date Q1 2013 Complete siting approvals Begin Construction Q4 2011 New Hampshire Siting (SEC) application filed Oct 2010 DOE Pre
Slide 16: 2001-2015 Transmission Capital Expenditures
2001-2015 Transmission Capital Expenditures $845 million of additional forecasted projects SWCT projects total $1.6 billion NEEWS projects ramping up $0 $100 $200 $300 $400 $500 $600 $700 $800 Base Reliability Major Southwest CT NEEWS Northern Pass Historic Forecast $2.9 Billion $2.8 Billion NU’s sh
Slide 17: In Millions
In Millions Northeast Gui vanes
Slide 18: Slide 18
Slide 19: NU Actual and Projected Transmission Year-End Rate Base
NU Actual and Projected Transmission Year-End Rate Base $2,099 $2,178 $2,234 $2,394 $2,552 $315 $341 $360 $406 $406 $505 $2,149 $2,114 $540 $183 $269 $459 $650 $730 $803 $834 $830 $0 $500 $1,000 $1,500 $2,000 $2,500 $3,000 $3,500 $4,000 $4,500 $5,000 Actual Actual CL&P PSNH WMECO Northern Pass Trans
Slide 20: Efforts Under Way to Bring Northern New England Wind Generation to Market
Efforts Under Way to Bring Northern New England Wind Generation to Market • New England RPS requirements are 21% by 2020, and existing resources provide only 6% • Complement current ISO-NE regional planning and potential FERC changes • Create efficiencies by optimizing multiple wind sites and requir
Slide 21: Electric Distribution and Generation Capital Expenditures – By Company
$305 $337 $320 $317 $329 $336 $84 $113 $117 $127 $132 $132 $1 Electric Distribution and Generation Capital Expenditures – By Company 2011 – 2015 Capital Expenditures $83 $133 $10 $22 $9 $5 $5 $5 $33 $36 $39 $39 $40 $177 $112 $52 $52 $29 $40 $29 $0 $50 $100 $150 $200 $250 $300 $350 $400 $450 $500 $55
Slide 22: NU Generation Strategy
NU Generation Strategy WMECO Solar Initiative Installation of 6 MW solar projected by 2012 Estimated cost: $41 million Completed 1.8 MW of solar at first site in Pittsfield, MA in October 2010 4.2 MW site in Springfield, MA on capped landfill, identified for second project Constructive regulatory mo
Slide 23: Yankee Gas Capital Expenditures
Yankee Gas Capital Expenditures $25 $30 $48 $50 $51 $52 $30 $37 $31 $30 $31 $33 $13 $16 $20 $20 $21 $22 $27 $30 $13 $26 $26 $0 $10 $20 $30 $40 $50 $60 $70 $80 $90 $100 $110 $120 $130 $140 $150 Actual Aging Infrastructure Basic Business Peak Load / New Business WWL Gas supply infrastructure 2011-2015
Slide 24: Waterbury to Wallingford Project to Add Needed Supply for System Demand
Waterbury to Wallingford Project to Add Needed Supply for System Demand • Fills gaps in supply portfolio • Eliminates system constraint in Cheshire area • Increases vaporization capacity of Waterbury LNG project • Yankee Gas’ $57.6 million expansion project began in April 2010 (Waterbury to Wallingf
Slide 25: 2009-2015: NU Actual and Projected Capital Expenditures and Depreciation
2009-2015: NU Actual and Projected Capital Expenditures and Depreciation Significant capital spending through 2015 $1,036 $1,209 $1,216 $969 $1,407 $1,428 $1,331 $310 $301 $305 $332 $359 $382 $413 $0 $200 $400 $600 $800 $1,000 $1,200 $1,400 $1,600 Actual Actual Total Capex (incl. cost of removal and
Slide 26: Slide 26
Slide 27: Slide 27
Slide 28: Capital Program Benefits Customers and Produces Attractive Rate Base Growth
$2,597 $2,933 $3,234 $3,370 $3,733 $4,725 $3,303 $3,670 $3,912 $4,171 $4,516 $4,893 $2,759 $3,488 Capital Program Benefits Customers and Produces Attractive Rate Base Growth $407 $405 $758 $773 $773 $763 $691 $682 $743 $756 $790 $426 $847 $969 $0 $2,000 $4,000 $6,000 $8,000 $10,000 $12,000 Actual Ac
Slide 29: NSTAR
NSTAR Company Update March 10, 2011
Slide 30: NSTAR Safe Harbor
NSTAR Safe Harbor Information Concerning Forward-Looking Statements In addition to historical information, this presentation may contain a number of “forward-looking statements” as defined in the Private Securities Litigation Reform Act of 1995. Words such as anticipate, expect, project, intend, pla
Slide 31: Slide 31
Slide 32: Slide 32
Slide 33: Slide 33
Slide 34: Premier Service Territory
Premier Service Territory • • Solid, diverse customer base Solid, diverse customer base • • Sales growth better than U.S. Sales growth better than U.S. overall overall • • Positive outlook for economy Positive outlook for economy
Slide 35: Customer Mix Provides Stability
Customer Mix Provides Stability 57% Commercial & Industrial 43% Residential 63% Residential 37% Commercial & Industrial Electric ($2.5 billion) Gas ($.5 billion) • Health Care • Education • Biotech • Government • Financial
Slide 36: A Long History of Negotiated, Multi-Year Distribution Rate Agreements
A Long History of Negotiated, Multi-Year Distribution Rate Agreements • years of rate agreements – last litigated rate increase in • Fully reconciling pension & post-retirement mechanism and recovery of energy supply • Current electric rate plan through December 31, 2012 • 10.5% ROE with +/- 2% neut
Slide 37: History of Disciplined Cost Control
History of Disciplined Cost Control $431 Total Operations & Maintenance Expense $447 $ IN MILLIONS $454 $431 • Productivity & automation focus • Performance driven culture • Engaged workforce and constructive union relations • Continuous improvement philosophy Key Drivers $447
Slide 38: 20 Consecutive Years of Operating Earnings Growth
…20 Consecutive Years of Operating Earnings Growth $2.37 $2.07 $2.22 $2.56 $2.60 - $2.75 Guidance
Slide 39: Consistent, Above Average Dividend Growth
Consistent, Above Average Dividend Growth …13 Consecutive Years of Increase… $1.30 $1.40 $1.50 $1.60 $1.70
Slide 40: Solid Results For 2010
Solid Results For 2010 2009 - EPS 2.37 $ Higher electric sales (+3.3%) and performance-based adjustment 0.21 Gas sales (-2.8%) (0.02) Higher transmission revenue 0.07 Lower interest costs 0.09 Increase in operations and maintenance (0.12) Decline in mitigation incentive revenues - transition costs (
Slide 41: Total Shareholder Return Outperforms the Industry
Total Shareholder Return Outperforms the Industry $1,000 $2,000 $3,000 $4,000 $5,000 $6,000 S&P 500 Utility Index NSTAR Only Company in Any Industry to Deliver 14 Consecutive Years of Positive Total Shareholder Return
Slide 42: Highest Credit Rating in the Industry
Highest Credit Rating in the Industry NSTAR A+ FPL Group, Inc. A Southern Company A Consolidated Edison, Inc. A- Dominion Resources, Inc. A- DPL Inc. A- Duke Energy Corporation A- Energy East Corporation A- KeySpan Corp. A- Niagara Mohawk Power Corporation A- Vectren Corporation A- ALLETE, Inc. BBB+
Slide 43: NSTAR System Has Significant Transmission Investment Ahead
NSTAR System Has Significant Transmission Investment Ahead • Transmission Rate Base is expected to double within 5 years to approximately $1.6 billion • Growth/reliability spending averages $100 million per year • Incremental Major Projects • Cape Cod Line $120 million (2011-2012) • South Boston Cir
Slide 44: JD Power Customer Surveys Recognize Our Efforts