Teck Resources Limited Class A · TSX:TECK.A
Teck Resources Limited Class A — Investor Day (March 2015)
35 slides from Teck Resources Limited Class A's investor day presentation, Mar 31, 2015
Slide 1: Fort Hills Update
Fort Hills Update March 31, 2015 Tim Watson, Senior Vice President, Project Development
Slide 2: Forward Looking Information
Fort Hills Update Forward Looking Information Both these slides and the accompanying oral presentation contain certain forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of the Securit
Slide 3: Strong Project Execution
Fort Hills Update Strong Project Execution All critical milestones being met Enhanced ability to deliver on time / on budget Staged execution strategy 3
Slide 4: Agenda
Fort Hills Update Agenda Staged Execution Strategy Impact of Lower Oil Prices Construction & Engineering Status Summary 4
Slide 5: Staged Execution Strategy
Fort Hills Update Staged Execution Strategy Key Elements • Staging the engineering release of the various project areas • Capturing global expertise through engineering & fabrication • Developed a logistics plan for off-shore module delivery • Enhancing the use of shop fabricated equipment & vessels
Slide 6: Recent Contracts Awarded
Fort Hills Update Recent Contracts Awarded • Ore Preparation Plant (OPP): Materials handling area awarded to FAM (Germany) - Significant fabrication and shop assembly by BOA Steel (China) • Secondary Extraction (ET): Awarded to SK Engineering (South Korea) - Extensive pipe, steel and module fabricat
Slide 7: Agenda
Fort Hills Update Agenda Staged Execution Strategy Impact of Lower Oil Prices Construction & Engineering Status Summary 7
Slide 8: Lower Oil Price Environment Provides Opportunities
Fort Hills Update Lower Oil Price Environment Provides Opportunities “Major projects in construction such as Fort Hills…will move forward as planned and take full advantage of the current economic environment. These are long-term growth projects that are expected to provide strong returns when they
Slide 9: Agenda
Fort Hills Update Agenda Staged Execution Strategy Impact of Lower Oil Prices Construction & Engineering Status Summary 9
Slide 10: Project Progressing Well
Fort Hills Update Project Progressing Well Solid Progress To 2014 Going Forward All 2014 critical milestones achieved 2015: Focus on detailed engineering, with continued ramp up of equipment delivery and construction Engineering ~70% complete - Ore preparation plant substantially complete - Extr
Slide 11: Overall Site Photo
Fort Hills Update Overall Site Photo River Water Intake Ore Prep Plant Robson Lodge Admin Complex Utilities & Cogen Primary Extraction Secondary Extraction Tailings Area Construction Trailers Flare Area 11
Slide 12: Site Plot Plan
Fort Hills Update Site Plot Plan Secondary Substation Extraction Athabasca River Extraction 1 Ore Prep & Tailings Highway #63 Operations Lodge MINE River Water Intake 12
Slide 13: Ore Preparation Plant
Fort Hills Update 1 Ore Preparation Plant North Mechanically- Stabilized Earth Wall Surge Bin Area Rotary Breaker Building Hydrotransport Corridor 13
Slide 14: Ore Preparation Plant
Fort Hills Update 1 Ore Preparation Plant Ore Preparation Plant – trunnion installed installation 14
Slide 15: Ore Preparation Plant – FAM Fabrication
Fort Hills Update 1 Ore Preparation Plant – FAM Fabrication 15
Slide 16: Ore Preparation Plant – FAM Fabrication
Fort Hills Update 1 Ore Preparation Plant – FAM Fabrication 16
Slide 17: Ore Preparation Plant – Saskarc Fabrication
Fort Hills Update 1 Ore Preparation Plant – Saskarc Fabrication Some pre-fabricated modules are arriving now 17
Slide 18: Site Plot Plan
Fort Hills Update Site Plot Plan Secondary Substation Extraction Athabasca River 2 Extraction 1 Ore Prep & Tailings Highway #63 Operations Lodge MINE River Water Intake 18
Slide 19: Extraction & Tailings Area – March 22, 2014
Fort Hills Update 2 Extraction & Tailings Area – March 22, 2014 19
Slide 20: Extraction & Tailings Area
Fort Hills Update 2 Extraction & Tailings Area Primary Separation Cells Column Flotation Building Tailings Pumphouse Building 20
Slide 21: Extraction & Tailings Area
Fort Hills Update 2 Extraction & Tailings Area Primary Separation Cells Tailings Thickeners & Flotation Columns Support Structure Modules 21
Slide 22: Site Plot Plan
Fort Hills Update Site Plot Plan Secondary 3 Substation Extraction Athabasca River 2 Extraction 1 Ore Prep & Tailings Highway #63 Operations Lodge MINE River Water Intake 25
Slide 23: Secondary Extraction
Fort Hills Update 3 Secondary Extraction First Stage Settler Overflow Solvent Bullets – Drum – Site Arrival Site Arrival Piling Installation 26
Slide 24: Secondary Extraction – Shop Fabrication
Fort Hills Update 3 Secondary Extraction – Shop Fabrication Steam Drum – High Pressure Boiler Cleaverbrooks, Nebraska Feedwater Pump & Drive – Flowserve, Argentina Shell & Tube Heat Exchanger – 30 Jiangsu Sunpower Technology, China
Slide 25: Secondary Extraction – Pipe Fabrication
Fort Hills Update 3 Secondary Extraction – Pipe Fabrication 31
Slide 26: Site Plot Plan
Fort Hills Update Site Plot Plan Secondary 3 4 Substation Extraction Athabasca River 2 Extraction 1 Ore Prep & Tailings Highway #63 Operations Lodge MINE River Water Intake 32
Slide 27: Main Substation
Fort Hills Update 4 Main Substation 33
Slide 28: Site Plot Plan
Fort Hills Update Site Plot Plan Secondary 3 4 Substation Extraction Athabasca River 2 Extraction 1 Ore Prep & Tailings Highway #63 Operations Lodge MINE 5 River Water Intake 34
Slide 29: River Water Intake
Fort Hills Update 5 River Water Intake 35
Slide 30: Site Plot Plan
Fort Hills Update Site Plot Plan Secondary 3 4 Substation Extraction Athabasca River 2 Extraction 1 Ore Prep & Tailings Highway #63 Operations 6 MINE Lodge 5 River Water Intake 36
Slide 31: Operations Lodge – April 30, 2014
Fort Hills Update 6 Operations Lodge – April 30, 2014 37
Slide 32: Mount Logan Operations Lodge
Fort Hills Update 6 Mount Logan Operations Lodge 38
Slide 33: Agenda
Fort Hills Update Agenda Staged Execution Strategy Impact of Lower Oil Prices Construction & Engineering Status Summary 39
Slide 34: Summary
Fort Hills Update Summary All critical milestones being met Enhanced ability to deliver on time / on budget Staged execution strategy 40
Slide 35: Fort Hills Update
Fort Hills Update March 31, 2015 Tim Watson, Senior Vice President, Project Development