Teck Resources Limited Class A · TSX:TECK.A

Teck Resources Limited Class A — Investor Day (March 2015)

35 slides from Teck Resources Limited Class A's investor day presentation, Mar 31, 2015

  1. Slide 1: Fort Hills Update

    Fort Hills Update March 31, 2015 Tim Watson, Senior Vice President, Project Development

  2. Slide 2: Forward Looking Information

    Fort Hills Update Forward Looking Information Both these slides and the accompanying oral presentation contain certain forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of the Securit

  3. Slide 3: Strong Project Execution

    Fort Hills Update Strong Project Execution All critical milestones being met Enhanced ability to deliver on time / on budget Staged execution strategy 3

  4. Slide 4: Agenda

    Fort Hills Update Agenda Staged Execution Strategy Impact of Lower Oil Prices Construction & Engineering Status Summary 4

  5. Slide 5: Staged Execution Strategy

    Fort Hills Update Staged Execution Strategy Key Elements • Staging the engineering release of the various project areas • Capturing global expertise through engineering & fabrication • Developed a logistics plan for off-shore module delivery • Enhancing the use of shop fabricated equipment & vessels

  6. Slide 6: Recent Contracts Awarded

    Fort Hills Update Recent Contracts Awarded • Ore Preparation Plant (OPP): Materials handling area awarded to FAM (Germany) - Significant fabrication and shop assembly by BOA Steel (China) • Secondary Extraction (ET): Awarded to SK Engineering (South Korea) - Extensive pipe, steel and module fabricat

  7. Slide 7: Agenda

    Fort Hills Update Agenda Staged Execution Strategy Impact of Lower Oil Prices Construction & Engineering Status Summary 7

  8. Slide 8: Lower Oil Price Environment Provides Opportunities

    Fort Hills Update Lower Oil Price Environment Provides Opportunities “Major projects in construction such as Fort Hills…will move forward as planned and take full advantage of the current economic environment. These are long-term growth projects that are expected to provide strong returns when they

  9. Slide 9: Agenda

    Fort Hills Update Agenda Staged Execution Strategy Impact of Lower Oil Prices Construction & Engineering Status Summary 9

  10. Slide 10: Project Progressing Well

    Fort Hills Update Project Progressing Well Solid Progress To 2014 Going Forward  All 2014 critical milestones achieved 2015: Focus on detailed engineering, with continued ramp up of equipment delivery and construction  Engineering ~70% complete - Ore preparation plant substantially complete - Extr

  11. Slide 11: Overall Site Photo

    Fort Hills Update Overall Site Photo River Water Intake Ore Prep Plant Robson Lodge Admin Complex Utilities & Cogen Primary Extraction Secondary Extraction Tailings Area Construction Trailers Flare Area 11

  12. Slide 12: Site Plot Plan

    Fort Hills Update Site Plot Plan Secondary Substation Extraction Athabasca River Extraction 1 Ore Prep & Tailings Highway #63 Operations Lodge MINE River Water Intake 12

  13. Slide 13: Ore Preparation Plant

    Fort Hills Update 1 Ore Preparation Plant North Mechanically- Stabilized Earth Wall Surge Bin Area Rotary Breaker Building Hydrotransport Corridor 13

  14. Slide 14: Ore Preparation Plant

    Fort Hills Update 1 Ore Preparation Plant Ore Preparation Plant – trunnion installed installation 14

  15. Slide 15: Ore Preparation Plant – FAM Fabrication

    Fort Hills Update 1 Ore Preparation Plant – FAM Fabrication 15

  16. Slide 16: Ore Preparation Plant – FAM Fabrication

    Fort Hills Update 1 Ore Preparation Plant – FAM Fabrication 16

  17. Slide 17: Ore Preparation Plant – Saskarc Fabrication

    Fort Hills Update 1 Ore Preparation Plant – Saskarc Fabrication Some pre-fabricated modules are arriving now 17

  18. Slide 18: Site Plot Plan

    Fort Hills Update Site Plot Plan Secondary Substation Extraction Athabasca River 2 Extraction 1 Ore Prep & Tailings Highway #63 Operations Lodge MINE River Water Intake 18

  19. Slide 19: Extraction & Tailings Area – March 22, 2014

    Fort Hills Update 2 Extraction & Tailings Area – March 22, 2014 19

  20. Slide 20: Extraction & Tailings Area

    Fort Hills Update 2 Extraction & Tailings Area Primary Separation Cells Column Flotation Building Tailings Pumphouse Building 20

  21. Slide 21: Extraction & Tailings Area

    Fort Hills Update 2 Extraction & Tailings Area Primary Separation Cells Tailings Thickeners & Flotation Columns Support Structure Modules 21

  22. Slide 22: Site Plot Plan

    Fort Hills Update Site Plot Plan Secondary 3 Substation Extraction Athabasca River 2 Extraction 1 Ore Prep & Tailings Highway #63 Operations Lodge MINE River Water Intake 25

  23. Slide 23: Secondary Extraction

    Fort Hills Update 3 Secondary Extraction First Stage Settler Overflow Solvent Bullets – Drum – Site Arrival Site Arrival Piling Installation 26

  24. Slide 24: Secondary Extraction – Shop Fabrication

    Fort Hills Update 3 Secondary Extraction – Shop Fabrication Steam Drum – High Pressure Boiler Cleaverbrooks, Nebraska Feedwater Pump & Drive – Flowserve, Argentina Shell & Tube Heat Exchanger – 30 Jiangsu Sunpower Technology, China

  25. Slide 25: Secondary Extraction – Pipe Fabrication

    Fort Hills Update 3 Secondary Extraction – Pipe Fabrication 31

  26. Slide 26: Site Plot Plan

    Fort Hills Update Site Plot Plan Secondary 3 4 Substation Extraction Athabasca River 2 Extraction 1 Ore Prep & Tailings Highway #63 Operations Lodge MINE River Water Intake 32

  27. Slide 27: Main Substation

    Fort Hills Update 4 Main Substation 33

  28. Slide 28: Site Plot Plan

    Fort Hills Update Site Plot Plan Secondary 3 4 Substation Extraction Athabasca River 2 Extraction 1 Ore Prep & Tailings Highway #63 Operations Lodge MINE 5 River Water Intake 34

  29. Slide 29: River Water Intake

    Fort Hills Update 5 River Water Intake 35

  30. Slide 30: Site Plot Plan

    Fort Hills Update Site Plot Plan Secondary 3 4 Substation Extraction Athabasca River 2 Extraction 1 Ore Prep & Tailings Highway #63 Operations 6 MINE Lodge 5 River Water Intake 36

  31. Slide 31: Operations Lodge – April 30, 2014

    Fort Hills Update 6 Operations Lodge – April 30, 2014 37

  32. Slide 32: Mount Logan Operations Lodge

    Fort Hills Update 6 Mount Logan Operations Lodge 38

  33. Slide 33: Agenda

    Fort Hills Update Agenda Staged Execution Strategy Impact of Lower Oil Prices Construction & Engineering Status Summary 39

  34. Slide 34: Summary

    Fort Hills Update Summary All critical milestones being met Enhanced ability to deliver on time / on budget Staged execution strategy 40

  35. Slide 35: Fort Hills Update

    Fort Hills Update March 31, 2015 Tim Watson, Senior Vice President, Project Development

Teck Resources — Investor Day (March 2015) on 6ix