Koné project construction on-budget and ahead of schedule • Continued exploration success • Robust liquidity sources
KONÉ CONSTRUCTION ACTIVITIES
EXPLORATION ACTIVITIES
FINANCIAL POSITION
VANCOUVER, British Columbia, May 14, 2026 (GLOBE NEWSWIRE) -- Montage Gold Corp. (“Montage” or the “Company”) (TSX: MAU, OTCQX: MAUTF) is pleased to report on its construction and exploration activities for Q1-2026, with highlights provided in Table 1 below.
Table 1: Business and financial highlights
| THREE MONTHS ENDED | ||||||||
| All amounts in millions of USD unless otherwise specified | Mar 31, 2026 | Dec 31, 2025 | Mar 31, 2025 | Δ Q1-2026 vs. Q4-2025 | ||||
| KONÉ CONSTRUCTION ACTIVITIES | ||||||||
| Cumulative hours worked, million hrs | 9.3 | 7.0 | 1.0 | +2.3 | ||||
| Lost-Time Injuries Frequency Rate | 0.11 | 0.20 | - | (0.09 | ) | |||
| Total cumulative capital committed, inclusive of amount disbursed | 606.9 | 540.6 | 217.5 | +66.3 | ||||
| - Cumulative capital disbursed1 | 504.9 | 367.0 | 84.6 | +137.9 | ||||
| - Cumulative capital committed and to be disbursed1 | 99.3 | 173.6 | 132.9 | (74.3 | ) | |||
| KONÉ EXPLORATION ACTIVITIES | ||||||||
| Meters drilled, meters | 47,254 | 28,915 | 45,887 | +18,339 | ||||
| Exploration expenditure1 | 7.5 | 5.8 | 6.9 | +1.7 | ||||
| CASH FLOW AND LIQUIDITY POSITION1 | ||||||||
| Cash flows used in investing activities | (110.3 | ) | (113.9 | ) | (56.7 | ) | +3.5 | |
| Cash flows (used in) generated from financing activities | (0.1 | ) | 157.3 | 0.4 | (157.4 | ) | ||
| Cash and cash equivalents, end of period | 79.4 | 191.8 | 42.7 | (112.4 | ) | |||
| Total liquidity and Koné project funding sources | 440.2 | 559.4 | 832.9 | (119.3 | ) | |||
| 1As referenced in the Company’s Financial Statements and Management’s Discussion and Analysis for the three months ended March 31, 2026, available on SEDAR+ and on the Company’s website. | ||||||||
The Company’s condensed interim consolidated Financial Statements and associated Management’s Discussion and Analysis for the three months ended March 31, 2026, have been filed under the Company’s profile on SEDAR+ (www.sedarplus.ca) and are available for download on the Company’s website.
Rapid construction progress continues to be made at the Company’s flagship Koné project, in Côte d’Ivoire, with first gold pour targeted ahead of schedule in late Q4-2026 through the oxide circuit, and remaining on-budget. A total of 2.3 million construction hours were worked in Q1-2026, with total hours worked now totalling +10.4 million hours from the commencement of the project until today, with a Lost Time Injury Frequency Rate (“LTIFR”) of 0.11.
Significant progress is being made on the key processing infrastructure ahead of an oxide start-up, with the successful installation of all major components in the mill, completion of the oxide sizer, erection of all reagent tanks and installation of the pre-leach thickener shell. Following successful hydro-testing of all the tanks on the carbon in leach ("CIL") trains, installation of agitators, gearboxes, inter-tank screens and launder systems are now ongoing, and tracking ahead of schedule. Construction of the hard rock circuit continues to advance on schedule, with civil works now progressing across the primary crusher, secondary crusher and high-pressure grinding rollers (“HPGR”). Construction of the tailings storage facility (“TSF”) is nearing completion with the laydown of high-density polyethylene (“HDPE”) liners over 90% complete. Other key infrastructure including the construction of the 225kV electrical substation and preparation for grid connection continues to progress on schedule with all towers erected and power line stringing well underway. A total of $606.9 million of capital had been committed as at quarter-end (inclusive of $504.9 million disbursed), which has further increased to approximately $636.9 million as at today, representing approximately 72% of the total $885.0 million capital expenditure, with prices in line with expectations.
In parallel, the Company continues to be focused on unlocking value through its exploration programmes. At the Koné project, a total of 47,254 meters were drilled in Q1-2026 with exploration efforts continuing to focus on infill and extension drilling of deposits, advancing pre-resource targets toward maiden resource definition, and testing of new targets. Updated Mineral Resource Estimates for satellite deposits, including Gbongogo South, Koban North, ANV, Yeré North, Lokolo Main, Sena and Diouma North and maiden Mineral Resource Estimates for new discoveries such as Petit Yao, Soman 1 & 2 and Lokolo West are expected to be published in Q2-2026. At Didievi, following the successful completion of the acquisition of African Gold Limited (“African Gold”; ASX:A1G) on April 29, 2026, the 40,000-meter exploration programme that was launched in 2025 is nearing completion, with results expected to be published in late Q2-2026, which are expected to be followed by an updated Mineral Resource Estimate. In addition, exploration works have begun across Montage’s recently secured greenfield properties including the Wendé property in Côte d’Ivoire where drilling is underway, and at the Sfariat and Zednes properties in Mauritania where early reconnaissance work is underway.
Martino De Ciccio, Chief Executive Officer of Montage, commented: “We are very pleased with Montage’s strong start to the year as we continue to advance our strategy of creating a premier, multi-asset African gold producer and delivering value for all our stakeholders.
Construction at our flagship Koné project, in Côte d’Ivoire, continues to progress at a rapid pace with completion of the oxide sizer and installation of all major components of the mill positioning us for a first gold pour through an oxide circuit start-up in late Q4-2026. On the exploration front, efforts have rapidly advanced in Q1-2026 to take advantage of the dry season, with over half of the budgeted exploration meters already completed. We have continued to delineate high grade satellites with the goal of supplementing production from the onset, and look forward to publishing updated resource estimates for satellites, along with maiden resource estimates for new targets over the coming weeks.
With the recent successful closing of the African Gold transaction, we added the high-quality Didievi project in Côte d’Ivoire, where we are completing a 40,000-meter drill programme which is expected to yield an updated resource estimate. Meanwhile, through the permit awarding process we have secured the Wendé advanced greenfield property in Côte d’Ivoire, where where a 9,000-meter drill programme is underway, and five permits across the Sfariat and Zednes exploration blocks in Mauritania where exploration efforts recently commenced.
We are very pleased with the continued progress across our business and look forward to continuing to execute on our strategy while delivering value for all our stakeholders.”
KONÉ PROJECT UPDATE
Construction continues to progress on-budget with rapid progress made across a number of key workstreams as summarized below:
Figure 1: Process plant area overview
Figure 2: Process plant key infrastructure
Figure 3: Hard-rock comminution circuit stages
Figure 4: Koné and Gbongogo mine services areas
Figure 5: Explosive magazine earthworks at Koné
Figure 6: Electrical substation and high-voltage grid connection preparation
Figure 7: Marahoué river bridge construction
Figure 8: TSF development and HDPE liner laydown
Timeline to first gold pour
Given the strong advancement in construction activities, the Company remains on-budget and is targeting first gold pour in late Q4-2026 through the oxide circuit, whilst the hard-rock comminution circuit remains on-schedule for completion in Q2-2027. Key upcoming milestones are presented in Table 2 below.
| Table 2: Koné project timeline to first gold pour | ||||||||||
| Work Stream | Q1-2025 | Q2-2025 | Q3-2025 | Q4-2025 | Q1-2026 | Q2-2026 | Q3-2026 | Q4-2026 | Q1-2027 | Q2-2027 |
| Tailings Dam & Water Dams | ||||||||||
| Tailings Dam | * | * | * | * | ||||||
| Water Storage & Dam | * | * | ||||||||
| Construction | ||||||||||
| Power Supply | * | * | * | * | * | |||||
| Site Infrastructure | * | * | * | * | * | * | * | |||
| Earth works & Concrete Works | * | * | * | * | * | * | ||||
| Structural, Mechanical, Piping | * | * | * | * | * | * | ||||
| Electrical | * | * | * | * | ||||||
| Process Plant Commissioning | * | * | * | |||||||
| First Gold - Oxide Circuit | * | |||||||||
| First Gold - Hard-Rock Circuit | * | |||||||||
As previously published, the Company expects to publish an updated life of mine plan (“LOM”) for the Koné project later this year to incorporate updated resources from Koné, Gbongogo Main and additional higher-grade satellite deposits, as well as the initiatives currently underway to further unlock value including the oxide circuit, process plant design enhancements, and the shift to an owner-operated mining model.
CASH FLOW, LIQUIDITY SOURCES AND CAPITAL REQUIREMENTS
Cash flows used in investing activities totalled $110.3 million in Q1-2026, a $3.6 million decrease from $113.9 million in Q4-2025. This variance was primarily driven by $10.6 million in proceeds from disposal of marketable securities, primarily offset by the timing of cash outflows related to construction expenditures at the Koné project. Cash flows used in financing activities in Q1-2026 was $0.1 million, representing a $157.4 million decrease from $157.3 million of cash flow generated in financing activities Q4-2025, as $156.25 million of the Wheaton Stream was drawn down in Q4-2025.
As at March 31, 2026, the Company had a consolidated cash balance of $79.4 million, compared to $191.8 million as at December 31, 2025, a decrease of $112.4 million mostly driven by $120.6 million spent in investment in mineral properties plant and equipment related to Koné project development, and the rest in exploration and business development costs, and administration expenditures, offset by the $10.6 million proceeds from disposal of marketable securities.
As at March 31, 2026, the Company had total liquidity and Koné project funding sources of $440.2 million, comprised of $331.3 million of undrawn funding sources (composed of the $156.3 million Wheaton Stream which was subsequently drawn on April 10, 2026, the $50.0 million Zijin Loan Facility, the $75.0 million Wheaton Loan Facility, and the $50.0 million AFG Working Capital Facility which was closed on April 17, 2026), $79.4 million of cash on hand and $29.6 million of other liquid assets. In addition, the Company has $72.3 million of undrawn CAT Equipment Financing.
A total of $606.9 million of capital had been committed for construction of the Koné project as at March 31, 2026 (inclusive of amounts disbursed), which further increased to $636.9 million as of today, representing 72% of the total $885.0 million capital expenditure estimate, with costs in line with expectations. As at March 31, 2026, a total of $504.9 million has been disbursed for construction of the Koné project, of which $137.9 million in Q1-2026, with approximately $280.1 million remaining to be disbursed until first gold pour through the oxide circuit in late Q4-2026, and a total of approximately $380.1 million remaining to be disbursed to completion of the hard-rock comminution circuit (inclusive of contingencies).
EXPLORATION ACTIVITIES
The 2026 group exploration spend, excluding activities linked to the African Gold assets following the close of its acquisition on April 29, 2026, is expected to amount to $18.0 million and comprise a total of 99,000 meters of drilling along with non-drilling exploration activities. The programme includes expenditure of $14.0 million at the Koné project amounting to 90,000 meters of drilling, $2.0 million of expenditure at the Wendé advanced greenfield exploration property amounting to 9,000 meters of drilling, and $2.0 million of expenditure in Mauritanian exploration properties on early-stage exploration works.
Koné project in Côte d’Ivoire
Didievi project in Côte d’Ivoire
Wendé advanced greenfield exploration property in Côte d’Ivoire
Mauritanian exploration properties
SUSTAINABILITY REPORT
In May 2026, Montage published its inaugural sustainability report, marking an important milestone in the Company’s sustainability journey and solidifying Montage’s commitment to transparency, accountability, and continuous improvement. The 2025 sustainability report outlines Montage’s key sustainability priorities, management systems, and performance indicators. Montage has adopted the GRI framework as the foundation for sustainability reporting with an intention to further enhance sustainability disclosures in future reports by incorporating additional internationally recognized standards along with third-party external assurance. The report is available on the Company’s website here.
KEY UPCOMING CATALYSTS
ABOUT MONTAGE GOLD
Montage Gold Corp. (TSX:MAU) is a Canadian-listed company focused on becoming a premier multi-asset African gold producer, with its flagship Koné project, located in Côte d’Ivoire, at the forefront. Based on the Updated Feasibility Study published in 2024 (the “UFS”), the Koné project has an estimated 16-year mine life and sizeable annual production of +300koz of gold over the first 8 years and is expected to enter production in late Q4-2026.
QUALIFIED PERSONS STATEMENT
The scientific and technical contents of this press release have been verified and approved by Mr. Peder Olsen, a Qualified Person pursuant to NI 43-101. Mr. Olsen, President and Chief Development Officer of Montage, is a registered Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM).
CONTACT INFORMATION
| For Investor Relations Inquiries: Jake Cain Strategy & Investor Relations Manager jcain@montagegold.com +44-7788-687-567 | For Media Inquiries: John Vincic Oakstrom Advisors john@oakstrom.com +1-647-402-6375 | For Regulatory Inquiries: Kathy Love Corporate Secretary klove@montagegold.com +1-604-512-2959 |
FORWARD-LOOKING STATEMENTS
This press release contains certain forward-looking information and forward-looking statements within the meaning of Canadian securities legislation (collectively, “Forward-looking Statements”). All statements, other than statements of historical fact, constitute Forward-looking Statements. Words such as “will”, “intends”, “proposed” and “expects” or similar expressions are intended to identify Forward-looking Statements. Forward-looking Statements in this press release include statements related to the Company’s objectives of achieving first gold pour in late Q4-2026 through an oxide circuit startup, and remaining on-schedule for completion of the hard-rock comminution circuit in the second quarter of 2027; the items listed under the heading “Key Upcoming Catalysts”; the Company’s mineral reserve and resource estimates; results of ongoing and planned exploration and drill programmes, including results of the pre-production drilling programme; expected recoveries and grades of the Koné project; timing in respect of the commencement and completion of construction of various components of the Koné project, the length of construction and of the mining operations at the Koné project, including estimated construction costs; timing and amount of necessary financing related to the mining operations at the Koné project; the timing and amount of future production from the Koné project; anticipated mining and processing methods of the Koné project; anticipated mine life of the Koné project; anticipated operational efficiencies and flexibility and other benefits of the construction of the oxide circuit; the publication of new resource estimates and updated LOM plan in 2026; and further information related to exploration programmes, exploration results and timing thereof at the Didievi project, the Wendé property and the Company’s exploration properties in Mauritania.
Forward-looking Statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that any Forward-looking Statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements, including that the returns from the Koné project will be lower than estimated, that additions to the mineral resources will not be achieved (including the failure to delineate Petit Yao into a high-grade satellite of scale) or that the remaining cost of construction of the Koné project will be higher than estimated, that the updated LOM plan will indicate lower financial returns or production, or that the acquisition of African Gold will not result in any benefits to Montage. Important factors that could cause actual results to differ materially from include uncertainties inherent in the preparation of mineral reserve and resource estimates and definitive feasibility studies, and in delineating new mineral reserve and resource estimates, including but not limited to, assumptions underlying the production estimates not being realized, incorrect cost assumptions, decreases in the price of gold, unexpected variations in quantity of mineralized material, grade or recovery rates being lower than expected, unexpected adverse changes to geotechnical or hydrogeological considerations, or expectations in that regard not being met, unexpected failures of plant, equipment or processes (including construction equipment), delays in or increased costs for the delivery of construction equipment and services, unexpected changes to availability of power or the power rates, failure to maintain permits and licenses, higher than expected interest or tax rates, adverse changes in project parameters, unanticipated delays and costs of consulting and accommodating rights of local communities, environmental risks inherent in the Côte d’Ivoire, title risks, including failure to renew concessions, unanticipated commodity price and exchange rate fluctuations, delays in or failure to receive access agreements or amended permits, and other risk factors set forth in the Company’s Annual Information Form available at www.sedarplus.ca, under the heading “Risk Factors”. The Company undertakes no obligation to update or revise any Forward-looking Statements, whether as a result of new information, future events or otherwise, except as may be required by law. New factors emerge from time to time, and it is not possible for Montage to predict all of them, or assess the impact of each such factor or the extent to which any factor, or combination of factors, may cause results to differ materially from those contained in any Forward-looking Statement. Any Forward-looking Statements contained in this press release are expressly qualified in their entirety by this cautionary statement.
