Business
Hombre Muerto West (HMW) Phase 1 Construction Update - Nanofiltration Plant Delivered to Site
Highlights: Nanofiltration plant successfully delivered to HMW site Galan and Authium teams have commenced on-site assembly. Assembly expected to be completed over the coming weeks Evaporation (sylvinite) ponds for Phase 1 operations completed Overall ...

About this update from Galan Lithium Limited
[{"type":"text","content":"Highlights:","length":11,"tagName":"p"},{"type":"list","items":[{"val":[{"type":"text","content":"Nanofiltration plant successfully delivered to HMW site","length":55,"tagName":"p"}]},{"val":[{"type":"text","content":"Galan and Authium teams have commenced on-site assembly. Assembly expected to be completed over the coming weeks","length":112,"tagName":"p"}]},{"val":[{"type":"text","content":"Evaporation (sylvinite) ponds for Phase 1 operations completed","length":62,"tagName":"p"}]},{"val":[{"type":"text","content":"Overall Phase 1 construction now approximately 85% complete","length":59,"tagName":"p"}]},{"val":[{"type":"text","content":"First processed brine expected early Q2 2026. First lithium chloride concentrate targeted in H1 2026","length":100,"tagName":"p"}]}],"tagName":"ul","bulletedList":true,"length":388,"olType":false},{"type":"text","content":"PERTH, AU / ACCESS Newswire / February 15, 2026 / Galan Lithium Limited (ASX:GLN) (Galan or the Company) is pleased to provide an update on construction progress at its 100% owned Hombre Muerto West (HMW) Project in Catamarca Province, Argentina.","length":246,"tagName":"p"},{"type":"text","content":"Commenting from the HMW site Galan's Managing Director, Juan Pablo (JP) Vargas de la Vega, said:","length":100,"tagName":"p"},{"type":"text","content":""Our HMW site team is very excited at the arrival of the nanofiltration plant. Over the past 2 years we have accumulated a lithium brine inventory of around 9,500 tonnes (LCE) in the HMW ponds. In the short term we plan to complete the nanofiltration plant assembly and commissioning, which will allow for the first processed lithium brine to be produced from HMW.","length":369,"tagName":"p"},{"type":"text","content":"The nanofiltration plant has been designed, tested, constructed and transported on an accelerated project schedule. I would like to recognise Authium's and Galan's teams who have come together in a spirit of partnership to make this possible."","length":256,"tagName":"p"},{"type":"text","content":"Nanofiltration Plant Delivered and Assembly Underway","length":52,"tagName":"p"},{"type":"text","content":"The Company confirms that the nanofiltration plant for Phase 1 operations has successfully arrived at the HMW project site.","length":123,"tagName":"p"},{"type":"text","content":"Galan's technic...