Endeavour Silver Provides Q4 2024 Construction Progress Update on Terronera; Surface Construction Progress Nearly 90% Complete
VANCOUVER, British Columbia, Feb. 07, 2025 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) provides a Q4 2024 co

About this update from Endeavour Silver Corp.
[{"type":"text","content":" VANCOUVER, British Columbia, Feb. 07, 2025 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. (\"Endeavour\" or the \"Company\") (NYSE: EXK; TSX: EDR) provides a Q4 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos. All dollar ($) references in this news release are in United States dollars. PDF.js viewer Thumbnails Document Outline Attachments Layers Current Outline Item Previous Next Highlight All Match Case Match Diacritics Whole Words Color Size Color Thickness Opacity Open Print Save Presentation Mode Current Page Go to First Page Go to Last Page Rotate Clockwise Rotate Counterclockwise Text Selection Tool Hand Tool Page Scrolling Vertical Scrolling Horizontal Scrolling Wrapped Scrolling No Spreads Odd Spreads Even Spreads Document Properties… Toggle Sidebar Find Previous Next Open Print Save Text Draw Tools Zoom Out Zoom In Automatic Zoom Actual Size Page Fit Page Width 50% 75% 100% 125% 150% 200% 300% 400% Enter the password to open this PDF file: Cancel OK File name: - File size: - Title: - Author: - Subject: - Keywords: - Creation Date: - Modification Date: - Creator: - PDF Producer: - PDF Version: - Page Count: - Page Size: - Fast Web View: - Close Preparing document for printing… 0% Cancel Substantial progress was achieved on Terronera’s Upper Plant Platform during the fourth quarter with systems commissioning underway. Focus continues on the Lower Platform. “Endeavour Silver’s Terronera Project is nearing completion,” commented Don Gray, Chief Operating Officer. “Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters. We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early Q2 2025.” Q4 2024 Construction and Development Highlights Site works and activities as of December 31, 2024: Safety – The Health and Safety Program and Procedures are complete and ready for transition from construction and commissioning into operations. Community Relations – Community sup...