Tempo TES Project Update: Brenmiller Energy Set to Begin Installation of its Storage Modules - bCubes(TM) - in May 2025 and Start Commissioning in October 2025

Brenmiller is replacing Tempo's fossil fuel boilers with a 32 MWh bGen™ thermal energy storage system delivering sustainable process heat expected to mitigate 6,200 tons of carbon emissions annually and save Tempo an estimated $7.5 million in ...

articleBrenmiller Energy LtdMay 9, 20255/company/brenmiller-energy-ltd-ordinary-shares/news/tempo-tes-project-brenmiller-energy-120000664
Tempo TES Project Update: Brenmiller Energy Set to Begin Installation of its Storage Modules - bCubes(TM) - in May 2025 and Start Commissioning in October 2025

About this update from Brenmiller Energy Ltd

[{"type":"list","items":[{"val":[{"type":"text","content":"Brenmiller is replacing Tempo's fossil fuel boilers with a 32 MWh bGen™ thermal energy storage system delivering sustainable process heat expected to mitigate 6,200 tons of carbon emissions annually and save Tempo an estimated $7.5 million in energy costs over 15 years","length":283,"tagName":"p"}]},{"val":[{"type":"text","content":"Tempo, partially owned by Heineken International B.V., is one of Israel's largest producers and distributors of beverage for brands including Heineken and Pepsi","length":164,"tagName":"p"}]}],"tagName":"ul","bulletedList":true,"length":447,"olType":false},{"type":"text","content":"TEL AVIV, IL / ACCESS Newswire / May 9, 2025 / Brenmiller Energy Ltd. ("Brenmiller", "Brenmiller Energy" or the "Company") (Nasdaq:BNRG), a leading global provider of thermal energy storage ("TES") solutions for industrial and utility customers, announced today that it is on track to meet its next four major contractual milestones and complete Stage 1 of its groundbreaking TES project for Tempo Beverages Ltd. ("Tempo") in early July 2025.","length":492,"tagName":"p"},{"type":"list","items":[{"val":[{"type":"text","content":"Construction of the TES base began in early April 2025, following completion of the required civil work by Tempo. Brenmiller expects to complete Stage 1 of the project in early July 2025 by meeting the following key milestones: completion of the base structure on May 12th, 2025, completion of the base insulation in the third week of May 2025 and installation of the first half of the bCubes™ in the last week of May 2025.","length":423,"tagName":"p"}]}],"tagName":"ul","bulletedList":true,"length":423,"olType":false},{"type":"list","items":[{"val":[{"type":"text","content":"Stage 2 of the project, which includes the installation of the remaining bCubes™ and insulation, is expected to take place in the second half of July 2025.","length":155,"tagName":"p"}]}],"tagName":"ul","bulletedList":true,"length":155,"olType":false},{"type":"list","items":[{"val":[{"type":"text","content":"Construction of the TES is expected to be completed in September 2025 with commissioning set to begin in October 2025.","length":118,"tagName":"p"}]}],"tagName":"ul","bulletedList":true,"length":118,"olType":false},{"type":"text","con...

More updates from Brenmiller Energy Ltd

TESAvi BrenmillerTempothe companyBrenmiller Energy Ltdthermal energy storageBrenmiller Energy